(DEc. 2008 Planning)
Ligne 14: Ligne 14:
 
* ATLAS Disk space : ATLASUSERDISK on T1 SE (fail-over for outputs in case of problems with T2 disk storage)
 
* ATLAS Disk space : ATLASUSERDISK on T1 SE (fail-over for outputs in case of problems with T2 disk storage)
 
* GRIF and CC-IN2P3 TOP BDII : should be available as they are used remotely by some sites
 
* GRIF and CC-IN2P3 TOP BDII : should be available as they are used remotely by some sites
 +
 +
=== Target and metrics ===
 +
* Nb of events : Few hundred up to 1000 jobs/site
 +
* Rate (evt/s) : up to 15 Hz
 +
* Efficiency (success/failure rate) : 80 %
 +
* CPU utilization :  CPUtime / Walltime > 50 %
 +
 
==== FR Cloud ST (2009 plans) ====
 
==== FR Cloud ST (2009 plans) ====
 
* See http://lcg.in2p3.fr/wiki/index.php/Atlas:Analysis_ST_2009
 
* See http://lcg.in2p3.fr/wiki/index.php/Atlas:Analysis_ST_2009
Ligne 61: Ligne 68:
 
* Dec 17 : <b> restart of MC production</b>
 
* Dec 17 : <b> restart of MC production</b>
 
* Dec 17 : <b> Beginning of Analysis Challenge (Phase 2) </b>
 
* Dec 17 : <b> Beginning of Analysis Challenge (Phase 2) </b>
 
=== Target and metrics ===
 
* Nb of events : Few hundred up to 1000 jobs/site
 
* Rate (evt/s) : up to 15 Hz
 
* Efficiency (success/failure rate) : 80 %
 
* CPU utilization :  CPUtime / Walltime > 50 %
 

Version du 15:28, 29 janvier 2009

02/12/08 : E.Lançon, F.Chollet
Thanks to Johannes Elmsheuser, Dan van der Ster, Cédric Serfon

Information & Contact

Mailing list ATLAS-LCG-OP-L@in2p3.fr

Goals

  • measure "real" analysis job efficiency and turn around on several sites of a given cloud
  • measure data access performance
  • check load balancing between different users and different analysis tools (Ganga vs pAthena)
  • check load balancing between analysis and MC production

Required services @ T1 and GRIF

  • LFC catalog : lfc-prod.in2p3.fr
  • ATLAS Disk space : ATLASUSERDISK on T1 SE (fail-over for outputs in case of problems with T2 disk storage)
  • GRIF and CC-IN2P3 TOP BDII : should be available as they are used remotely by some sites

Target and metrics

  • Nb of events : Few hundred up to 1000 jobs/site
  • Rate (evt/s) : up to 15 Hz
  • Efficiency (success/failure rate) : 80 %
  • CPU utilization : CPUtime / Walltime > 50 %

FR Cloud ST (2009 plans)

First exercise on the FR Cloud (December 2008)

Phase 1 : Site stress test oraganized by ATLAS and run centrally in a controlled manner (2 days)

DA challenges have been performed on IT and DE clouds in october 08. Proposition has been made to extend this cloud-by cloud challenge to the FR Cloud. See ATLAS coordination DA challenge meeting (Nov. 20)

First exercise will help to identify breaking points and bottlenecks. It is limited in time (a few days) and requires careful attention of site administrators during that period,in particular network (internal & external), disk, cpu monitoring. This first try (Stress tests) can be run centrally in a controlled manner. The testing framework is ganga-based.

Sites: IN2P3-LPC, GRIF-LPNHE, TOKYO-LCG2, IN2P3-CPPM 
Max Jobs Per Site: 300
Sites: TOKYO
Max Jobs Per Site: 300
Input DS Patterns: mc08.*Wmunu*.recon.AOD.e*_s*_r5*tid* 
                   mc08.*Zprime_mumu*.recon.AOD.e*_s*_r5*tid* 
                   mc08.*Zmumu*.recon.AOD.e*_s*_r5*tid* 
                   mc08.*T1_McAtNlo*.recon.AOD.e*_s*_r5*tid* 
                   mc08.*H*zz4l*.recon.AOD.e*_s*_r5*tid* 
                   mc08.*.recon.AOD.e*_s*_r5*tid*
ST summary
Phase 2 : Pathena Analysis Challenge
  • Data Analysis exercice open to physicists with their favorite application
  • Physicists involved : Julien Donini, Arnaud Lucotte, Bertrand Brelier, Eric Lançon, LAL ?, LPNHE ?
Dec. 2008 Planning
  • Dec 8 : stop of MC production
  • Dec. 8-9: 1rst round with Tokyo, CPPM, LPC (LAN limited to 1Gbps), GRIF-LPNHE
  • Dec 17 : restart of MC production
  • Dec 14 : stop of MC production
  • Dec. 15-16 : 2nd round with LAPP, CC-IN2P3-T2 (to be confirmed), Tokyo, CPPM, LPC, possibly GRIF (SACLAY, IRFU, LPNHE), RO-07 and RO-02
  • Dec 17 : restart of MC production
  • Dec 17 : Beginning of Analysis Challenge (Phase 2)